NEW QUESTION 155
What is an off-specification?

  • A. A type of issue
  • B. A major risk
  • C. A new requirement
  • D. A quality tolerance

Answer: A

Explanation:
Section: Volume A

 

NEW QUESTION 156
A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?

  • A. Write an Exception Report
  • B. Raise an off-specification
  • C. Raise a request for change
  • D. Amend the Work Package

Answer: B

 

NEW QUESTION 157
What is a supplier of a PRINCE2 project responsible for?

  • A. Providing resources to deliver the project outputs
  • B. Realizing the benefits from the project
  • C. Establishing the project's governance
  • D. Providing the project mandate

Answer: A

Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wikidot.com/senior-supplier

 

NEW QUESTION 158
Which is a purpose of an End Project Report?

  • A. Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed
  • B. Identify individuals or groups that need to be told that the project is coming to an end
  • C. Ensure that key project information is archived and made secure
  • D. Review how well the project performed against the Project Initiation Documentation used to authorize it

Answer: D

Explanation:
Section: Volume B

 

NEW QUESTION 159
Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business.

  • A. products
  • B. project management team
  • C. stages
  • D. controls

Answer: A

 

NEW QUESTION 160
Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment?

  • A. Ensure the technical integrity of aproject
  • B. Specify the desired result
  • C. Develop a project's products
  • D. Provide the resources and skills to deliver the desired result

Answer: B

 

NEW QUESTION 161
Identify the missing word in the following sentence.
[ ? ] is the measurable decline resulting from a negative outcome.

  • A. An off-specification
  • B. An exception
  • C. A dis-benefit
  • D. A risk

Answer: C

 

NEW QUESTION 162
Why is a project brief produced?

  • A. To provide a full and firm foundation for the initiation of a project
  • B. To be used by the project board as a basis for reviewing the progress of a project
  • C. To act as a trigger for the 'starting up a project' process
  • D. To record the how the project will communicate with its stakeholders

Answer: A

 

NEW QUESTION 163
Which is a responsibility of the project board?

  • A. To ensure effective communication with external stakeholders
  • B. To ensure production of the project's outputs
  • C. To manage the team managers and project support
  • D. To implement the change control approach

Answer: A

Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Organization#Project_Board

 

NEW QUESTION 164
What is the minimum number of management stages required by PRINCE2?

  • A. Four stages: to start, to initiate, to deliver and to close the project
  • B. Three stages: to initiate, to deliver and to close the project
  • C. Two stages: to initiate and to deliver the project
  • D. One stage: to cover the whole project

Answer: C

Explanation:
Section: Volume B

 

NEW QUESTION 165
Which role is part of the Project Board?

  • A. Risk owner
  • B. Senior Supplier
  • C. Project Manager
  • D. Corporate or programme management

Answer: B

 

NEW QUESTION 166
What should influence the Project Board's decision whether to delegate its Project Assurance responsibilities?

  • A. The need to involve key stakeholders on the project management team
  • B. Having insufficient time to perform the role
  • C. The preference of the Project Manager
  • D. Having insufficient authority to perform the role

Answer: B

 

NEW QUESTION 167
How does PRINCE2 ensure that the specific management needs of an organization are met?

  • A. By representing best practice
  • B. By mandating training
  • C. By focusing on viability
  • D. By incorporating tailoring

Answer: A

 

NEW QUESTION 168
Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?

  • A. Project Initiation Documentation
  • B. Benefits Review Plan
  • C. Project mandate
  • D. Project Brief

Answer: A

 

NEW QUESTION 169
How many management stages should a PRINCE2 project consist of?

  • A. Start up stage, initiation stage and at least one other management stage to cover the remainder of the project
  • B. Initiation stage and at least one other management stage to cover the remainder of the project
  • C. Start up stage, at least one other management stage to cover the remainder of the project and a closing stage
  • D. Start up stage, initiation stage and a closing stage

Answer: B

 

NEW QUESTION 170
According to the 'tailor to suit the project' principle, what is the basis for effective project management?

  • A. That the appropriate number and type of meetings are held
  • B. That the appropriate information is provided to make decisions
  • C. That the project method relates to the project's environment
  • D. That the project is divided into an appropriate number of stages

Answer: C

Explanation:
Explanation/Reference:
Reference http://prince2.wiki/Tailor_to_suit_the_project_environment

 

NEW QUESTION 171
What should be considered when defining the number of management stages in a project?

  • A. When highlight reports will be submitted
  • B. When key decisions need to be made
  • C. When project support will be available
  • D. When the team managers are available

Answer: B

Explanation:
Explanation/Reference:
Reference https://www.prince2primer.com/prince2-management-and-technical-stages/

 

NEW QUESTION 172
What is a benefits management approach used to assess?

  • A. The effectiveness of the project strategies
  • B. How the project's products have performed when in operational use
  • C. The suitability of the project management team structure
  • D. How the project has progressed against its plans

Answer: B

Explanation:
Explanation
Reference https://mplaza.pm/prince2-benefits-management-approach-template/

 

NEW QUESTION 173
Which is an objective of the Starting up a Project process?

  • A. Authorize the Project Manager to proceed with the initiation stage
  • B. Agree how the project will be monitored and controlled after initiation
  • C. Identify who will be responsible for creating the Project Plan
  • D. Agree how issues and changes will be identified, assessed and controlled

Answer: C

 

NEW QUESTION 174
Which is a minimum requirement for applying the change theme?

  • A. To appoint the project manager as part of the change authority
  • B. To record every issue that is raised in the issue register
  • C. To define the project's approach to baselining products
  • D. To establish a change budget to fund changes in scope

Answer: B

Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Themes#Change_Theme

 

NEW QUESTION 175
What is the result of the change derived from using the project's product?

  • A. Outcome
  • B. Benefit
  • C. Output
  • D. Dis-benefit

Answer: A

 

NEW QUESTION 176
Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment?

  • A. Specify the desired result
  • B. Ensure the technical integrity of a project
  • C. Develop a project's products
  • D. Provide the resources and skills to deliver the desired result

Answer: A

Explanation:
Section: Volume A

 

NEW QUESTION 177
......

PRINCE2 PRINCE2-Foundation Pre-Exam Practice Tests | DumpStillValid: https://www.dumpstillvalid.com/PRINCE2-Foundation-prep4sure-review.html