NEW QUESTION 153
Whose approval is needed to replace a Stage Plan with an Exception Plan?

  • A. Team Manager
  • B. Corporate orprogramme management
  • C. Project Board
  • D. Project Manager

Answer: C

 

NEW QUESTION 154
During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?

  • A. End Stage Report
  • B. Team Plan
  • C. Project Plan
  • D. Work Package

Answer: C

 

NEW QUESTION 155
Which is a benefit of using PRINCE2?

  • A. Can be tailored by leaving out elements of the method for some projects
  • B. Can be applied to any type of project
  • C. Enables the management of projects as well as of 'business as usual' activities
  • D. Avoids the need to involve corporate or programme management

Answer: B

 

NEW QUESTION 156
Which is the purpose of the Change theme?

  • A. Prevent change to baselined products
  • B. Assess and control uncertainty
  • C. Establish mechanisms to monitor and compare actual achievements against those planned
  • D. Identify, assess and control any potential and approved changes to baselined products

Answer: D

 

NEW QUESTION 157
Which is a purpose of a Risk Register?

  • A. Capture risks that may occur during the project
  • B. Record the risk tolerance for the project
  • C. Record how risk management activities will be undertaken on the project
  • D. Capture issues which are impacting on the delivery of the project objectives

Answer: A

Explanation:
Section: Volume B

 

NEW QUESTION 158
Identify the missing word in the following sentence. The guiding obligations and good practices which determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.

  • A. Themes
  • B. Principles
  • C. Techniques
  • D. Processes

Answer: B

 

NEW QUESTION 159
Which characteristic distinguishes a project from regular business operations?

  • A. Introduces business change
  • B. Produces benefits
  • C. Incurs cost
  • D. Manages stakeholders

Answer: A

 

NEW QUESTION 160
Which role does NOT set tolerances?

  • A. Change Authority
  • B. Corporate or programme management
  • C. Project Manager
  • D. Project Board

Answer: A

 

NEW QUESTION 161
Which is a type of issue?

  • A. An Exception Report
  • B. A lesson
  • C. A request for change
  • D. A risk with an estimated high impact

Answer: C

Explanation:
Section: Volume A

 

NEW QUESTION 162
Identify the missing words in the following sentence.
A problem/concern, a request for change and [ ? ] are the three types of issue.

  • A. an off-specification
  • B. a threat
  • C. a constraint
  • D. a deviation from tolerance

Answer: A

 

NEW QUESTION 163
Identify the missing words in the following sentence.
The 'managing a stage boundary' process should be executed [ ? ] a management stage.

  • A. when a stage plan has been prepared for
  • B. at, or close to the end of,
  • C. when all the delivery steps have been completed within
  • D. at the beginning of

Answer: B

Explanation:
Explanation/Reference:
Reference https://publications.axelos.com/Prince2Agile2015/content.aspx?
showNav=true&expandNav=true&page=cros_131

 

NEW QUESTION 164
How does PRINCE2 ensure that the specific management needs of an organization are met?

  • A. By incorporating tailoring
  • B. By representing best practice
  • C. By mandating training
  • D. By focusing on viability

Answer: B

Explanation:
Section: Volume B

 

NEW QUESTION 165
Which are characteristics of stakeholders?
1. They are often affected by the project
2. They agree with every project objective
3. They are only/always external to the corporate organization
4. They typically interact with the project

  • A. 1 and 2
  • B. 3 and 4
  • C. 2 and 3
  • D. 1 and 4

Answer: D

Explanation:
Explanation
Reference https://www.prince2.com/blog/how-to-identify-stakeholders/

 

NEW QUESTION 166
Which two roles are linked by the Managing Product Delivery process?

  • A. Project Manager and Team Manager
  • B. Corporate or programme management and Project Board
  • C. Team Manager and external supplier
  • D. Project Board and Project Manager

Answer: A

Explanation:
Section: Volume A

 

NEW QUESTION 167
As a minimum requirement for applying the risk theme, what must specifically be assessed?

  • A. Whether a risk may alter the project's business justification
  • B. Whether a risk may impact the underlying technical assumptions
  • C. Whether a risk may cause the project to exceed its cost tolerance
  • D. Whether a risk may affect the project-level quality tolerances

Answer: A

 

NEW QUESTION 168
Which is NOT a purpose of the Initiating a Project process?

  • A. Enable an organization to understand the work that needs to be done to deliver a project's products before a project is approved
  • B. Enable the Project Board to decide whether it is worthwhile to initiate a project
  • C. Enable a Project Board decision about the commitment of resources to a project
  • D. Establish solid foundations for a project

Answer: B

Explanation:
Section: Volume A

 

NEW QUESTION 169
According to the 'continued business justification' principle, what should happen to the funds when a project can no longer be justified?

  • A. They should be used to deliver a reduction in the scope of the project
  • B. They should be used to create an alternative business case for the project
  • C. They should be returned to corporate, programme management or customer
  • D. They should be transferred back to the project board to reassign

Answer: C

Explanation:
Section: Volume B

 

NEW QUESTION 170
Identify the missing words in the following sentence.
The 'directing a project' process starts when [ ? ] and is triggered by the request to initiate a project.

  • A. the project board has agreed the project strategies
  • B. the 'starting up a project' process is completed
  • C. corporate, programme management or the customer have authorized a project
  • D. the project mandate has been approved by the project board

Answer: B

Explanation:
Explanation/Reference:
Reference https://www.siliconbeachtraining.co.uk/blog/prince2-directing-project-process-dp

 

NEW QUESTION 171
......