NEW QUESTION 40
Which statement is FALSE?

  • A. A project's output is any of the project's specialist products
  • B. A project outcome perceived to be negative by one or more stakeholders is a dis-benefit
  • C. A project benefit is only realized after the project has closed
  • D. A project outcome is the resultof the change derived from using the project's outputs

Answer: C

 

NEW QUESTION 41
Who represents the three project interests on a project?

  • A. Project board
  • B. External project stakeholders
  • C. Project support
  • D. Project manager

Answer: A

Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Organization#Three_Project_Interests

 

NEW QUESTION 42
Which is a purpose of the 'initiating a project' process?

  • A. To enable the project board to decide whether it is worthwhile to initiate a project
  • B. To provide a fixed point at which acceptance for the project product is confirmed
  • C. To produce a stage plan for each stage of a multi-stage project
  • D. To enable an organization to understand the work needed to deliver the project's products

Answer: A

Explanation:
Explanation
Reference
http://prince2.wiki/Initiating_a_Project#Objective

 

NEW QUESTION 43
Which of the following statements about stakeholders are true?
1 . Someone who thinks they will be affected by a project is a stakeholder on that project
2 . Stakeholders may be internal or external to the corporate organization

  • A. Only 2 is true
  • B. Neither 1 or 2 are true
  • C. Both 1 and 2 are true
  • D. Only 1 is true

Answer: C

 

NEW QUESTION 44
Which should be funded by a change budget?

  • A. Handover activities
  • B. Increase in agreedscope
  • C. Increase in agreed scope
  • D. Increase in agreed scope

Answer: B

 

NEW QUESTION 45
Which process is triggered towards the end of the final stage when all the assigned work has been completed?

  • A. Closing a Project
  • B. Managing Product Delivery
  • C. Managing a Stage Boundary
  • D. Controlling a Stage

Answer: A

Explanation:
Section: Volume A
Explanation

 

NEW QUESTION 46
What is the result of the change derived from using the project's product?

  • A. Benefit
  • B. Output
  • C. Outcome
  • D. Dis-benefit

Answer: C

Explanation:
Section: Volume B

 

NEW QUESTION 47
Which is a PRINCE2 time-driven control?

  • A. End Stage Report
  • B. Project Brief
  • C. Project Initiation Documentation
  • D. Checkpoint Report

Answer: D

 

NEW QUESTION 48
Which product describes the method the project will use to engage with corporate, programme management or the customer?

  • A. Benefits management approach
  • B. Communication management approach
  • C. Change control approach
  • D. Quality management approach

Answer: D

 

NEW QUESTION 49
Which is NOT a requirement of a Stage Plan?

  • A. Produced near to the end of the previous management stage
  • B. Approved and signed-off by Project Assurance
  • C. Produced to an appropriate level of detail to enable day-to-day control
  • D. Approved at the end of a management stage

Answer: B

 

NEW QUESTION 50
Which is a purpose of the quality theme?

  • A. To establish how the project will ensure that all products created meet their requirements
  • B. To establish baselines against which any changes to products can be assessed
  • C. To determine the communication needs of the organization's quality assurance function
  • D. To identify all the products of the project to ensure the scope has been adequately defined

Answer: A

 

NEW QUESTION 51
Which is a purpose of the Risk Register?

  • A. Act as a central record of information relating to the identified risks for the project
  • B. List the responsibilities for achieving an effective risk management procedure
  • C. Describe the risk management techniques and standards to be applied to the project
  • D. Act as a repository forinformal issues

Answer: A

 

NEW QUESTION 52
Which theme estimates the cost of delivering the project?

  • A. Business case
  • B. Plans
  • C. PROGEESS
  • D. Change

Answer: A

Explanation:
Explanation
Reference http://prince2.wiki/Business_Case

 

NEW QUESTION 53
What process aims to ensure accurate progress information is provided to the Project Manager?

  • A. Managing Product Delivery
  • B. Starting up a Project
  • C. Managing a Stage Boundary
  • D. Directing a Project

Answer: A

 

NEW QUESTION 54
Which theme defines the accountability for realization of the project's benefits?

  • A. Progress
  • B. Plans
  • C. Organization
  • D. Quality

Answer: C

 

NEW QUESTION 55
Which is a purpose of the Risk theme?

  • A. Establish a procedure to ensure every change is agreed by the relevant authority before it takes place
  • B. Establish mechanisms to manage risks at the corporate or programme level of an organization
  • C. Establish mechanisms to control any unacceptable deviations from plan
  • D. Establish a cost-effective procedure to identify, assess and control uncertainty

Answer: D

 

NEW QUESTION 56
Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.

  • A. risk
  • B. product
  • C. quality
  • D. supplier

Answer: D

 

NEW QUESTION 57
What process aims to ensure accurate progress information is provided to the Project Manager?

  • A. Managing Product Delivery
  • B. Starting up a Project
  • C. Managing a Stage Boundary
  • D. Directing a Project

Answer: A

 

NEW QUESTION 58
Identify the missing word in the following sentence.
The PRINCE2 method addresses project management with four integrated elements: principles, themes, [ ? ] and tailoring PRINCE2 to the project environment.

  • A. activities
  • B. processes
  • C. products
  • D. quality

Answer: B

Explanation:
Section: Volume B
Explanation/Reference: http://www.innolead.co.bw/index.php/inno-content/cid/27/prince2/

 

NEW QUESTION 59
......

PRINCE2-Foundation PDF Dumps Are Helpful To produce Your Dreams Correct QA's: https://www.dumpstillvalid.com/PRINCE2-Foundation-prep4sure-review.html

PRINCE2-Foundation Practice Test Dumps with 100% Passing Guarantee: https://drive.google.com/open?id=1nCSmtGbUQ4xis89SfDEhCjsP-3wLqrRp