NEW QUESTION 75
In the Develop Project Team process, which of the following is identified as a critical factor for a project's success?

  • A. Virtual teams
  • B. Team meetings
  • C. Teamwork
  • D. Subcontracting teams

Answer: C

Explanation:
Explanation/Reference:
Explanation:
Process: 9.3 Develop Project Team
Definition: The process of improving competencies, team member interaction, and overall team environment to enhance project performance. The key benefit of this process is that it results in improved teamwork, enhanced people skills and competencies, motivated employees, reduced staff turnover rates, and improved overall project performance.
Key Benefit: The key benefit of this process is that it results in improved teamwork, enhanced people skills and competencies, motivated employees, reduced staff turnover rates, and improved overall project performance.
Inputs
1. Human resource management plan
2. Project staff assignments
3. Resource calendars
Tools & Techniques
1. Interpersonal skills
2. Training
3. Team-building activities
4. Ground rules
5. Colocation
6. Recognition and rewards
7. Personnel assessment tools
Outputs
1. Team performance assessments
2. Enterprise environmental factors updates

 

NEW QUESTION 76
The process of estimating the type and quantity of material, human resources, equipment, or supplies required to perform each activity is known as:

  • A. Conduct Procurements.
  • B. Collect Requirements.
  • C. Estimate Activity Resources.
  • D. Estimate Activity Durations.

Answer: C

Explanation:
Explanation/Reference:
Explanation:
Process: 6.4 Estimate Activity Resources
Definition: The process of estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity.
Key Benefit: The key benefit of this process is that it identifies the type, quantity, and characteristics of resources required to complete the activity which allows more accurate cost and duration estimates.
Inputs
1. Schedule management plan
2. Activity list
3. Activity attributes
4. Resource calendars
5. Risk register
6. Activity cost estimates
7. Enterprise environmental factors
8. Organizational process assets
Tools & Techniques
1. Expert judgment
2. Alternative analysis
3. Published estimating data
4. Bottom-up estimating
5. Project management software
Outputs
1. Activity resource requirements
2. Resource breakdown structure
3. Project documents updates

 

NEW QUESTION 77
A project manager has just completed several brainstorming sessions and has gathered the data to show commonality and differences in one single place.
What technique was followed?

  • A. Affinity diagram
  • B. Collective decision making
  • C. Multicriteria decision analysis
  • D. Mind mapping

Answer: D

 

NEW QUESTION 78
One of the key benefits of the Plan Human Resource Management process is that it:

  • A. establishes project roles and responsibilities.
  • B. outlines team selection guidelines and team member responsibilities.
  • C. provides an accurate appraisal of team member performance.
  • D. improves teamwork, interpersonal skills, and competencies.

Answer: A

 

NEW QUESTION 79
Which of the following statements is true regarding project and product lifecycles?

  • A. A single product lifecycle can only have one project lifecycle.
  • B. A single product lifecycle may consist of multiple project lifecycles.
  • C. A single project lifecycle may consist of multiple product lifecycles.
  • D. A product lifecycle is always shorter than the project lifecycle.

Answer: B

Explanation:
Section: Volume D

 

NEW QUESTION 80
The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success. The engagement level of the stakeholders should be classified as:

  • A. Leading
  • B. Neutral
  • C. Supportive
  • D. Resistant

Answer: A

Explanation:
Section: Volume C

 

NEW QUESTION 81
A project is in the planning phase. The project manager is considering different elements that may influence or constrain the project.
Which of the following internal enterprise environmental factors should the project manager consider?

  • A. Market conditions
  • B. Legal restrictions
  • C. Industry standards
  • D. Employee capability

Answer: D

Explanation:
Section: Volume E

 

NEW QUESTION 82
Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?

  • A. Cost performance index (CPI)
  • B. Variance at completion (VAC)
  • C. Budget at completion (BAC)
  • D. Cost variance (CV)

Answer: A

 

NEW QUESTION 83
Which tool or technique is effective in a project in which the deliverable is not a service or result?

  • A. Variance analysis
  • B. Decomposition
  • C. Inspection
  • D. Product analysis

Answer: D

 

NEW QUESTION 84
Which tool or technique is an examination of industry and specific vendor capabilities?

  • A. Bidder conferences
  • B. Market research
  • C. Independent estimates
  • D. Analytical techniques

Answer: B

 

NEW QUESTION 85
Which of the following documents should the project manager update as a result of implementing the Plan Risk Responses process?

  • A. Issue Log
  • B. Assumption Log
  • C. Risk Management Plan
  • D. Risk Report

Answer: C

 

NEW QUESTION 86
A project lifecycle is defined as:

  • A. a process required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
  • B. the application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.
  • C. a recognized standard for the project management profession.
  • D. a collection of generally sequential and sometimes overlapping project phases.

Answer: D

Explanation:
Section: Volume E
Explanation/Reference:
Explanation:
2.4 Project Life Cycle
A project life cycle is the series of phases that a project passes through from its initiation to its closure. The phases are generally sequential, and their names and numbers are determined by the management and control needs of the organization or organizations involved in the project, the nature of the project itself, and its area of application. The phases can be broken down by functional or partial objectives, intermediate results or deliverables, specific milestones within the overall scope of work, or financial availability. Phases are generally time bounded, with a start and ending or control point. A life cycle can be documented within a methodology.
The project life cycle can be determined or shaped by the unique aspects of the organization, industry, or technology employed.
While every project has a definite start and a definite end, the specific deliverables and activities that take place in between will vary widely with the project. The life cycle provides the basic framework for managing the project, regardless of the specific work involved.

 

NEW QUESTION 87
An input to the Manage Project Team process is:

  • A. Work performance reports.
  • B. Enterprise environmental factors.
  • C. Activity resource requirements.
  • D. Change requests.

Answer: A

Explanation:
Explanation/Reference:
Explanation:
Process: 9.4 Manage Project Team
Definition: The process of tracking team member performance, providing feedback, resolving issues, and managing changes to optimize project performance.
Key Benefit: The key benefit of this process is that it influences team behavior, manages conflict, resolves issues, and appraises team member performance.
Inputs
1. Human resource management plan
2. Project staff assignments
3. Team performance assessments
4. Issue log
5. Work performance reports
6. Organizational process assets
Tools & Techniques
1. Observation and conversation
2. Project performance appraisals
3. Conflict management
4. Interpersonal skills
Outputs
1. Change requests
2. Project management plan updates
3. Project documents updates
4. Enterprise environmental factors updates
5. Organizational process assets updates

 

NEW QUESTION 88
The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:

  • A. idea/mind mapping technique.
  • B. Delphi technique,
  • C. nominal group technique.
  • D. majority rule technique.

Answer: C

 

NEW QUESTION 89
Variance and trend analysis is a tool and technique used in which process?

  • A. Perform Qualitative Risk Analysis
  • B. Control Risks
  • C. Plan Risk Responses
  • D. Perform Quantitative Risk Analysis

Answer: B

Explanation:
Section: Volume B
Explanation:
Process: 11.6 Control Risks
Definition: The process of implementing risk response plans, tracking identified risks, monitoring residual risks, identifying new risks, and evaluating risk process effectiveness throughout the project.
Key Benefit: The key benefit of this process is that it improves efficiency of the risk approach throughout the project life cycle to continuously optimize risk responses.
Inputs
1. Project management plan
2. Risk register
3. Work performance data
4. Work performance reports
Tools & Techniques
1. Risk reassessment
2. Risk audits
3. Variance and trend analysis
4. Technical performance measurement
5. Reserve analysis
6. Meetings
Outputs
1. Work performance information
2. Change requests
3. Project management plan updates
4. Project documents updates
5. Organizational process assets updates

 

NEW QUESTION 90
A tool and technique used during the Collect Requirements process is:

  • A. alternatives identification.
  • B. product analysis.
  • C. expert judgment.
  • D. prototypes.

Answer: D

 

NEW QUESTION 91
The process of prioritizing risks for further analysis or action is known as:

  • A. Perform Qualitative Risk Analysis.
  • B. Plan Risk Responses.
  • C. Plan Risk Management.
  • D. Perform Quantitative Risk Analysis.

Answer: A

Explanation:
Explanation/Reference:
Explanation:
Process: 11.3 Perform Qualitative Risk Analysis
Definition: The process of prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact.
Key Benefit: The key benefit of this process is that it enables project managers to reduce the level of uncertainty and to focus on high-priority risks.
Inputs
1. Risk management plan
2. Scope baseline
3. Risk register
4. Enterprise environmental factors
5. Organizational process assets
Tools & Techniques
1. Risk probability and impact assessment
2. Probability and impact matrix
3. Risk data quality assessment
4. Risk categorization
5. Risk urgency assessment
6. Expert judgment
Outputs
1. Project documents updates

 

NEW QUESTION 92
Updates to organizational process assets such as procurement files, deliverable acceptances, and lessons learned documentation are typical outputs of which process?

  • A. Control Procurements
  • B. Close Project or Phase
  • C. Conduct Procurements
  • D. Close Procurements

Answer: D

 

NEW QUESTION 93
The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:

  • A. Critical path methodology.
  • B. Forecasting.
  • C. Earned value management.
  • D. Critical chain methodology.

Answer: C

 

NEW QUESTION 94
In which process is a project manager identified and given the authority to apply resources to project activities?

  • A. Manage Project Execution
  • B. Develop Project Management Plan
  • C. Develop Project Charter
  • D. Acquire Project Team

Answer: C

Explanation:
Section: Volume D
Explanation:
Process: 4.1. Develop Project Charter
Definition: The process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Key Benefit: The key benefit of this process is a well-defined project start and project boundaries, creation of a formal record of the project, and a direct way for senior management to formally accept and commit to the project.
Inputs
1. Project statement of work
2. Business case
3. Agreements
4. Enterprise environmental factors
5. Organizational process assets
Tools & Techniques
1. Expert judgment
2. Facilitation techniques
Outputs
1. Project charter

 

NEW QUESTION 95
......