To prepare for the SAP C-TS4CO-2021 certification exam, candidates can take advantage of various resources provided by SAP, including online training courses, SAP S/4HANA system access, and study materials. Additionally, candidates can also join SAP user communities and forums to interact with other professionals and gain insights into the latest trends and best practices in the field.
The SAP c_ts4co_2021 exam is a multiple-choice test that consists of 80 questions, and the candidates have 180 minutes to complete the exam. The exam is available in English, Japanese, and German languages. The passing score for the SAP c_ts4co_2021 exam is 63%, and the exam fee is $550. The exam can be taken online or in-person at an authorized SAP testing center.
NEW QUESTION # 42
What are some of the characteristics of planning for internal orders? Note: There are 2 correct answers to this question.
- A. You can enter costs and revenues.
- B. You can plan multiple versions.
- C. Availability control can check against plan values.
- D. You can define tolerance limits for plan overspend.
Answer: A,B
NEW QUESTION # 43
You want to create a new standard cost estimate based on the quantity structure of the existing standard cost estimate. Which object do you use?
- A. Reference variant
- B. Transfer control
- C. Costing type
- D. Costing version
Answer: B
NEW QUESTION # 44
How do you maintain number range intervals in Controlling?
- A. By document type
- B. By account type
- C. By business transactions
- D. By cost element category
Answer: C
NEW QUESTION # 45
You have implemented Product Cost by Sales Oder in conjunction with revenue-based results analysis in your organization.
For a particular sales order item, you have the following:
Plan revenue = 3000; Plan costs = 2000
Actual revenue = 1200; Actual costs = 1000
What data does the system calculate during results analysis?
- A. Revenue = 1200; Cost of sales = 800; WIP = 200
- B. Revenue = 1200; Cost of sales = 1000; Reserve = 200
- C. Revenue = 1200; Cost of sales = 1000; WIP = 200
- D. Revenue = 1200; Cost of sales = 800; Reserve = 200
Answer: A
NEW QUESTION # 46
Which field can you select for both reporting in costing based and account-based Profitability Analysis?
- A. Version
- B. Value in Controlling Area Currency
- C. Record type
- D. Cost element
Answer: A
NEW QUESTION # 47
Which type of Profitability Analysis updates the cost of goods sold at the time of delivery?
- A. Periodic-accounting based
- B. Both account-based and costing-based
- C. Account-based only
- D. Costing-based only
Answer: C
NEW QUESTION # 48
Which of the following statements best describe Product Cost by Period? Note: There are 2 correct answers to this question.
- A. It is used when the focus of controlling is on a stable and continuous production process.
- B. It is used in conjunction with a product cost collector.
- C. It is used when periodic costs outweigh daily postings.
- D. It is used to analyze work in process (WIP) based on actual costs.
Answer: A,B
NEW QUESTION # 49
What parameters can you set up when defining order types?
- A. Define source structure.
- B. Allow revenue postings.
- C. Define default parameters for master record fields.
- D. Define document type.
Answer: B,C
NEW QUESTION # 50
Which of the following statements best describe Product Cost by Order? Note: There are 2 correct answers to this question.
- A. It is recommended for products with a long production time.
- B. It is used when controlling by individual production lots or discrete quantities is needed.
- C. It is used when you perform repetitive manufacturing.
- D. It is used when full cost traceability is needed.
Answer: B,D
NEW QUESTION # 51
You are considering using commitment management with internal orders. What do you need to do in the configuration?
- A. Activate commitment management in both the controlling area and the order type.
- B. Activate commitment management only in the controlling area.
- C. Activate commitment management in the controlling area, the order type, and in individual internal order master data.
- D. Activate commitment management in both the version and the order type.
Answer: A
NEW QUESTION # 52
You want to run an assessment cycle in Profitability Analysis to allocate cost center costs during period-end closing for your organization. Which of the following objects is part of the assessment cycle?
- A. Cycle iteration
- B. Tracing factor
- C. Sender cost objects
- D. Template
Answer: B
NEW QUESTION # 53
You are creating new activity type and want to maintain plan prices for a cost center. Which attribute must you configure in the activity type master record? Note: There are 3 correct answers to this question.
- A. Price indicator
- B. Valid cost center categories
- C. Company code
- D. Activity type category
- E. CO version
Answer: A,B,D
NEW QUESTION # 54
You want to derive the profitability segment for a line item in the universal journal using SAP S/4HANA standard configuration. What requirements must be fulfilled? Note: There are 2 correct answers to this question.
- A. Account-based Profitability Analysis must be active.
- B. The type of the general ledger account must be primary cost/revenue or secondary cost.
- C. The type of the addressed ledger must be an extension ledger.
- D. Costing-based Profitability Analysis must be active.
Answer: A,B
NEW QUESTION # 55
Which of the following statements are applicable to automatic account assignment in SAP S/4HANA? Note:
There are 2 correct answers to this question.
- A. It can be defined for postings on general ledger accounts of primary costs type.
- B. It can be defined for postings on general ledger accounts of secondary costs type.
- C. It takes precedence over validation and substitution.
- D. It can be overwritten in the application.
Answer: A,C
NEW QUESTION # 56
Which statements best describes a single cost center standard hierarchy?
- A. It is a structure to which all the cost centers within a controlling area are assigned.
- B. It is a structure to which all cost center groups create for a controlling area are assigned.
- C. It is a structure to which all cost center groups created within an operating concern are assigned.
- D. It is a structure to which all the cost centers within an operating concern are assigned.
Answer: A
NEW QUESTION # 57
You have implemented Product Cost by Sales Oder in conjunction with cost-based POC results analysis in your organization.
For a particular sales order item, you have the following:
Plan revenue = 3000; Plan costs = 2000
Actual revenue = 1200; Actual cost=1000
What data does the system calculate during results analysis?
- A. "Revenue = 1500; Cost of sales = 1000; Capitalized revenue (revenue in excess of billings) = 300"
- B. "Revenue = 1200; Cost of sales = 1000; Capitalized revenue (revenue in excess of billings) = 200"
- C. "Revenue = 1200; Cost of sales = 1000; Revenue surplus =200"
- D. "Revenue = 1500; Cost of sales = 1000; Revenue surplus =300"
Answer: A
NEW QUESTION # 58
You create alternative CO versions for your controlling area, in addition to version 0. What would you use additional CO versions for? Note: There are 2 correct answers to this question.
- A. To store data of alternative plan costing runs
- B. To store different plan data
- C. To store different budget data
- D. To store data of parallel valuation
Answer: B,D
NEW QUESTION # 59
Which scenarios can be covered by one single costing run? Note: There are 2 correct answers to this question.
- A. Product cost collector cost estimate in one plant
- B. Current cost estimate of all the materials in all controlling area
- C. Inventory cost estimate of all the materials in one plant
- D. Standard cost estimate of all the materials in all plants of a controlling area
Answer: A,C
NEW QUESTION # 60
At which level do you define the valuation method for results analysis?
- A. Company code
- B. Plant
- C. Controlling area
- D. Operating concern
Answer: C
NEW QUESTION # 61
Which processes split costs into their primary cost components? Note: There are 2 correct answers to this question.
- A. Business process price calculation
- B. Settlement of internal orders
- C. Cost center/activity type price calculation
- D. Execution of the assessment cycles
Answer: A,C
NEW QUESTION # 62
......