NEW QUESTION 25
AACE International defines _____________as a technique of economic evaluation that sums over a given study period, the costs of initial investment, replacements, operations, and maintenance/repair; expressed in either present or annual value terms.

  • A. Life cycle costs method (LCC)
  • B. Net present worth method
  • C. Risk analysis
  • D. Benefit/Cost ratio (B/C) method

Answer: A

 

NEW QUESTION 26

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen., using the drop down menu, to reference during your response/choice of responses.
What is the range of unit costs?

  • A. $26.65
  • B. $48.22
  • C. $21.57
  • D. $485.00

Answer: D

 

NEW QUESTION 27

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
At the end of 30 months, the final price for the piece of equipment will be:

  • A. $370,710
  • B. $378,750
  • C. $328,810
  • D. $375,658

Answer: D

 

NEW QUESTION 28
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
Which of the following methods a used for creating critical path schedules:

  • A. Arrow diagram method
  • B. Precedence diagram method
  • C. Precedence and arrow diagram methods only
  • D. Gantt chart (bar chart) method

Answer: C

 

NEW QUESTION 29

The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
If the owner in B has as his primary goal to get the project completed and on line as fast as possible, then he would most likely use the ______________type of contract.

  • A. Cost plus
  • B. Lump sum
  • C. Lump sum + incentive
  • D. Unit Rate

Answer: C

 

NEW QUESTION 30
An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.
Answer the question using a straight line depreciation and a 10% interest rate.
The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
Present worth calculations is represented by which of the following equations?

  • A. Option D
  • B. Option B
  • C. Option A
  • D. Option C

Answer: A

 

NEW QUESTION 31
An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.
Answer the question using a straight line depreciation and a 10% interest rate.
The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
Assuming a 53% tax rate, how much cumulative depreciation will have been claimed at the end of the grain elevator's life span?

  • A. $37,600
  • B. $80,000
  • C. None
  • D. $42,400

Answer: B

 

NEW QUESTION 32

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
10,278 hours have been expended to date. The CPI at this point in time is 0.93. SPI is
1.03. How many hours were planned?

  • A. 10,586
  • B. 9,559
  • C. 9,280
  • D. 10,278

Answer: A

 

NEW QUESTION 33
Some of the principles of good communication are:

  • A. Use short words; avoid jargon; avoid acronyms and abbreviations; use complete sentences; have a beginning, middle and end; be accurate; be interested in what topic is being communicated
  • B. Tell the other person what to do; give insincere praise; psychoanalyze the other person; make light of a serious problem; do not gain the trust of anyone; always have a hidden agenda
  • C. The social process by which people in a specific situation construct meaning using symbolic behavior
  • D. Seek to clarify your ideas before communicating; examine the true purpose of each communication; consider the total physical and human setting whenever you communicate; be mindful, while you communicate, of the overtones as well as the basic content of the message

Answer: A

 

NEW QUESTION 34

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
What is the range of estimated quantities?

  • A. $45 to $530
  • B. $26.78 to $75.00
  • C. $48.22
  • D. $485

Answer: A

 

NEW QUESTION 35
An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.
Answer the question using a straight line depreciation and a 10% interest rate.
Which of the following interest rates disregards the effects of compounding periods that occur more frequent than annually?

  • A. Simple interest rate
  • B. Minimum attractive rate of return
  • C. Continuous compounding rate
  • D. Nominal interest rate

Answer: D

 

NEW QUESTION 36

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen., using the drop down menu, to reference during your response/choice of responses.
Calculate the weighted average unit cost.

  • A. $46.13
  • B. $47.63
  • C. $48.35
  • D. $48.09

Answer: C

 

NEW QUESTION 37
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
The latest allowable end time minus the earliest allowable end time on a schedule activity is referred to as:

  • A. Free float
  • B. Activity total slack
  • C. Remaining duration
  • D. Just-in-time" scheduling

Answer: B

 

NEW QUESTION 38
An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.
Answer the question using a straight line depreciation and a 10% interest rate.
Which of the following would NOT be considered part of a project cost and schedule forecast?

  • A. Usage of contingency
  • B. Current trends of time and money
  • C. Peripherals report
  • D. Changes to the project execution plan

Answer: C

 

NEW QUESTION 39
A work breakdown structure (WBS) is developed because:

  • A. It can be illustrated by individual bars for major phases, such as permitting, funding, engineering, procurement construction, commission/startup
  • B. It can be illustrated by a simple bar, with important milestones represented by symbols at the planned time of occurrence
  • C. It avoids omissions of key product activities through a systematic planning process; removes the complexity of the project by dividing it into manageable units; and provides a framework.
  • D. It defines specific tasks within a project from which schedules can be developed; it aids in linking activities with resources; it facilitates communication; and it allows integration of project plans

Answer: D

 

NEW QUESTION 40
Two of the most important things to know when planning a speech or lecture are the ______________and______________ of your audience.

  • A. Political preference, sense of humor
  • B. Motivation, professionalism
  • C. Background, attitude
  • D. Culture, understanding

Answer: D

 

NEW QUESTION 41

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
At the end of Year 3, steel prices will have increased by what percentage over today's price? (round to 1 decimal)

  • A. 8.7%
  • B. 4.6%
  • C. 8.2%
  • D. 8.0%

Answer: D

 

NEW QUESTION 42
A systematic coding structure for organizing and managing scope, assets, cost, resources, work and schedule activity information is a______________.

  • A. Schedule identification number
  • B. Cost breakdown structure
  • C. Code of accounts
  • D. Cost estimate classification

Answer: C

 

NEW QUESTION 43
An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.
Answer the question using a straight line depreciation and a 10% interest rate.
How much money should be set aside today to have $20,000 available eight (8) years from now if the interest rate is 6% compounded annually?

  • A. $31,875
  • B. $12,550
  • C. $13,515
  • D. $29,600

Answer: B

 

NEW QUESTION 44
......