Doubting study materials before buying is healthy; good ones welcome it. The 074-343 exam materials at DumpStillValid are written and checked by professional experts, and a free demo lets you inspect their quality yourself — no leap of faith required for the Microsoft Managing Projects with Microsoft Project 2013 content.
Microsoft 074-343 Exam Overview:
| Certification Vendor: | Microsoft |
|---|---|
| Exam Name: | Managing Projects with Microsoft Project 2013 |
| Exam Number: | 74-343 |
| Passing Score: | 700/1000 |
| Certificate Validity Period: | Does not expire |
| Real Exam Qty: | 20-35 tasks (performance-based) |
| Exam Price: | Approximately USD 100 (varies by region) |
| Exam Duration: | 50 minutes |
| Related Certifications: | Microsoft Office Specialist (MOS) Project 2013 Expert |
| Available Languages: | Chinese (Simplified), English, Japanese, German, French, Spanish |
| Exam Format: | Lab simulation, Task-driven assessment, Performance-based |
| Recommended Training: | Microsoft Learn - Project training |
| Exam Registration: | Microsoft Certification Portal |
| Sample Questions: | ![]() |
| Exam Way: | Available via authorized test centers or online proctored delivery (where supported) |
| Pre Condition: | No formal prerequisites required, recommended familiarity with Microsoft Project 2013 |
| Official Syllabus URL: | https://learn.microsoft.com/en-us/credentials/ |
Microsoft 074-343 Exam Syllabus Topics:
| Section | Objectives |
|---|---|
| Reporting and Communication | - Project reporting tools
|
| Managing Resources | - Resource allocation and optimization
|
| Managing Tasks | - Task creation and structure
|
| Creating and Managing a Project | - Project file creation and configuration
|
| Tracking Project Progress | - Monitoring and updating progress
|
074-343 Exam FAQ: Clear Answers for Busy People
The official outline structures the 074-343 exam around weighted domains such as:
- Creating and Managing a Project ()
- Managing Resources ()
- Reporting and Communication ()
In the Microsoft Managing Projects with Microsoft Project 2013 materials at DumpStillValid, the key knowledge points within these domains are clearly underlined, so the heavy areas get the attention they deserve without extra digging.
No formal prerequisites required, recommended familiarity with Microsoft Project 2013
The 074-343 exam is the official assessment for the Microsoft Managing Projects with Microsoft Project 2013 certification from Microsoft. It measures how well you can apply the published exam objectives in realistic scenarios — and for professionals looking to change their current situation, the credential is one of the most concrete ways to demonstrate new, verifiable skills.
Professional experts — and then other experts check their work. The 074-343 exam content is compiled by specialists deeply familiar with the real exam, who make the knowledge easy to understand and keep the descriptions vivid rather than dry. Before release, the materials go through repeated rounds of checking, and the key knowledge points are clearly underlined throughout. That two-layer process — written by experts, verified by experts — is what the quality of the DumpStillValid question bank rests on.
Passing the 074-343 exam requires 700/1000, and the registration fee is Approximately USD 100 (varies by region). Knowing your target score early turns practice sessions into measurable progress rather than guesswork.
Microsoft lists the following training resources:
Official courses explain the concepts; well-organized practice questions with underlined key points make revision fast. The two complement each other nicely.
The 074-343 exam contains 20-35 tasks (performance-based) questions with a time allowance of 50 minutes minutes. Practicing complete timed sets is the reliable way to make that pace feel manageable on the day.
Safe and automatic. The installation package from DumpStillValid is clean — no viruses, no bundled extras — and it arrives by email about a minute after payment. Afterwards, whenever a new version of the 074-343 exam materials is released, our system automatically emails it to you at once; you simply check your inbox regularly and download. This update service is free for 365 days, and extends at a 50% renewal discount beyond that.
Registration for the 074-343 exam is handled through the official channels below:
If you have the determination to change your current situation, booking a date is the moment that determination becomes a plan.
Microsoft Managing Projects with Microsoft Project 2013 Sample Questions:
You are using Microsoft Project Professional 2013.
Three years ago, you successfully completed a project to review all of the suppliers within your organization, and you have been asked to run a similar project again. You still have the project plan from three years ago.
You need to use the most efficient method to produce a new plan with tasks based upon the old project plan.
What should you do?
- A. Rename the old plan to a .mpt file, and select it from the featured templates to create the new project.
- B. Open the file in an earlier version of Project Professional and save it as a Project Professional 2013 file format. Open the file in Project Professional 2013.
- C. Use the New from existing project option to create the new project.
- D. Open the file, and copy and paste the task list into the schedule.
Correct Answer: C 🗳️
You are a project manager for a company that is based in New York and London. The company uses Project Professional 2013.
Teams from both offices are working together on a project. Since the two offices are located in different regions, the teams have separate company holiday schedules and working times.
You need to ensure that the effort for each resource and task is set up properly in the calendar.
You want to achieve this goal by using the least amount of time and effort.
What should you do?
- A. Assign the 24-hour calendar to all tasks and select Scheduling ignores resource calendars.
- B. Create a London calendar from the standard calendar and assign the London calendar as the project calendar.
- C. Create a new base calendar for London that includes all of the London office's company holidays and assign it to all London resources.
- D. Manually edit each London resource's calendar to add all of the London office's company holidays.
Correct Answer: C 🗳️
You are a project manager for a company that uses baselines in Project Standard 2013.
Project stakeholders approve an update to the baseline of a project in progress. You enter the new tasks necessary to include the project schedule changes.
You need to update the baseline for the new tasks.
What should you do?
- A. Delete the current baseline and re-baseline the entire project.
- B. Select the new tasks and set the baseline for the selected tasks.
- C. Select the new tasks and copy the schedule to the baseline1 fields for the selected tasks.
- D. Copy the current schedule to the baseline1fields.
Correct Answer: B 🗳️
You are a project manager who uses Project Standard 2013.
You manage a large project and are capturing actual work for the tasks as they are being worked.
You do not need to enter the time on the actual day worked; however, you need to capture the total amount of time spent on the task.
The fixed work task has a baseline of 20 hours, and the developer's timecard displays the following hours:
* Monday = 2 hours
* Tuesday = 8 hours
* Wednesday = 4 hours
* Thursday = 2 hours
* Friday = 2 hours
The developer informs you that the task is now complete.
You need to update the actual work and mark the task complete.
What should you do?
- A. Open the Task Form and format it to show Schedule Details. Enter 18 hours in the Actual Work for the resource. Enter 2 hours in the remaining work. Mark the task as 100% complete.
- B. Open the Task Form and format it to show Schedule View. Enter 18 hours in the Work column for the resource.
- C. Open the Task Form and format it to show Work Details. Enter 20 hours in the Actual Work for the resource. Enter 0 hours in the remaining work. Mark the task as 100% complete.
- D. Open the Task Form and format it to show Work Details. Enter 18 hours in the Actual Work for the resource. Enter 0 hours in the remaining work.
Correct Answer: D 🗳️
Your company uses Project Professional 2013.
You are building a schedule by using predecessors to help determine a logical duration.
The following image shows a baselined list of tasks with predecessors:
You have been told that Task C is optional, and you recommend inactivating the task to keep it visible on the schedule.
You need to determine what the results are to the schedule when inactivating Task C.
How should you answer?
- A. The finish date is reduced by six working days, cost is reduced by $400, and baseline cost is reduced by $400.
- B. The finish date is reduced by five working days, cost remains unchanged, and baseline cost is unchanged.
- C. The finish date is reduced by six calendar days, cost is reduced by $400, and baseline cost is unchanged.
- D. The finish date is reduced by four calendar days, cost is reduced by $400, and baseline cost is reduced by $400.
- E. The finish date is reduced by four working days, cost remains unchanged, and baseline cost is reduced by $400.
Correct Answer: C 🗳️